ENP Electro Novin ParsPower system testing & protection

Cable Testing (PD, VLF, Tan δ & more)

Insulation resistance, VLF, tan δ, partial discharge (PD) and fault location for MV and HV cables.

Power cables are the arteries of the network, and their failures are usually sudden and costly. Most faults start with insulation ageing, moisture ingress (water trees), voids and impurities inside the insulation, or poorly made joints and terminations. The right cable test prevents sudden failures and avoids wrong tests that damage healthy cables.

Cable test methods

TestPurposeApplication
Insulation resistance (IR)General health of insulation and earth connectionsBefore and after any other test; all cables
Sheath testFind damage to the outer sheath and moisture ingressAfter installation and during maintenance
VLF withstand test (0.1 Hz)Confirm the insulation withstands a voltage above normal serviceAcceptance of new cables, after repair and jointing
Tan δ (VLF-TD)Assess ageing and moisture in the insulation without damaging itService-aged XLPE cables; replace-or-continue decisions
Partial discharge (PD)Locate local weak spots in insulation, joints and terminationsAcceptance and condition assessment; offline and online
Fault location (TDR and pre-location)Determine distance and exact position of a failureAfter a short circuit or cable break
Route tracing and identificationFind the cable route and identify a cable among othersBefore excavation or repair
Phasing and continuityConfirm phase order and conductor/screen integrityBefore connection and energization

VLF testing — withstand at 0.1 Hz

A long cable behaves like a large capacitor. Testing at power frequency (50 Hz) needs very high power and a heavy set; at 0.1 Hz the required power is hundreds of times lower, so the equipment is portable and can be used on site. VLF is the standard method for testing MV XLPE cables.

  • Test voltage and duration follow the standard and project specification (IEEE 400.2, IEC 60060-3, IEC 60502-2); typically a multiple of the phase-to-earth voltage (U0) for 15 to 60 minutes
  • Cosine-rectangular or sinusoidal waveform; insulation is not over-stressed during the test
  • Pass = withstand for the full duration; a breakdown during the test means a weak point has been found
  • Warning: DC testing of XLPE cables is not recommended, as it injects space charge into the insulation and can damage the cable

Tan δ and insulation condition assessment

Tan δ is the dissipation factor of the insulation. New insulation has low losses; moisture and water trees raise it. By measuring tan δ at several voltage steps (e.g. 0.5, 1.0 and 1.5 × U0) we can:

  • Judge the mean value and its stability against IEEE 400.2 criteria
  • Classify cables as "good", "needs monitoring" or "action required"
  • Plan replacement instead of waiting for a sudden outage
  • Combine with a VLF test (Monitored Withstand)

Partial discharge (PD)

Partial discharge is a tiny spark inside voids or weak spots in the insulation that starts years before complete failure. PD is the most important early warning of failure in cables, joints, terminations and MV switchgear.

TypeMethodApplication
Offline (de-energized cable)VLF voltage or Damped AC (OWTS)Measure PD magnitude (pC), inception and extinction voltage (PDIV/PDEV) and locate the defect with TDR
Online (cable in service)HFCT, TEV and UHF sensorsMonitor cables, terminations and switchgear without an outage
  • Measurement per IEC 60270 and (for extruded cables) IEC 60885-3
  • Acceptance criteria follow the manufacturer's specification and the project standard
  • Results are reported as a PD map (location versus magnitude)

Cable fault location

  • Pre-location: TDR, arc reflection (ARM) and surge / multiple-impulse (SIM/MIM) methods to find the distance from the cable end
  • Pinpointing: surge generator with acoustic or magnetic-field receiver along the route
  • Route tracing: cable route tracer and identification to keep excavation small

When is it needed?

  • Acceptance testing of new cables before energization
  • After jointing, repair or termination work
  • Periodic monitoring of ageing cables in petrochemical, steel, power plants and distribution substations
  • After any fault and before re-energization

Safety and deliverables

  • Restricted area and warning signs; full discharge of the capacitive charge after the test and earthing of both cable ends
  • Official report with the voltage and duration of each test, tan δ plots and PD map
  • Comparison with previous results and a technical recommendation (continue, monitor, replace the faulty section)

Scope of work

  • VLF (0.1 Hz) withstand testing of XLPE cables
  • Tan δ and insulation ageing assessment
  • Offline and online partial discharge (PD) with location
  • Cable fault location (TDR and pinpointing) and route tracing
  • Insulation resistance, sheath, phasing and continuity tests
  • Official report with PD map and tan δ plots

Ready for your next project

Technical advice and price enquiries, free of charge.

Request a consultation →