ENP Electro Novin ParsPower system testing & protection

Comprehensive Substation Commissioning Checklist Before Energisation

Testing and commissioning09 Oct 2026ENP Technical Team3 min read

Energising without a structured review raises the risk of equipment damage, long production outages and danger to personnel. This checklist summarises typical commissioning stages for medium- and high-voltage substations. The final list for each project should follow the client's standards, manufacturers' instructions and the operator's regulations.

1. Documents and drawings

  • Match the as-built drawings with the actual installation, including single-line, control and terminal drawings
  • Review the short-circuit and protection coordination studies and obtain the approved relay settings
  • Review factory acceptance test (FAT) reports and type-test certificates
  • Complete installation records: bolt torque, alignment and clearances

2. Visual and mechanical inspection

  • Equipment condition, cleanliness and absence of transport damage
  • Torque check of busbar and cable connections
  • SF6 gas pressure in GIS and gas breakers, oil levels in transformers and bushings
  • Labelling, circuit identification and safety signs

3. Earthing system

  • Measure the substation earth resistance and check step and touch voltages
  • Verify continuity of equipment, panel and structure bonding to the earth grid

4. Equipment tests

  • Cables: megger test and, where required, VLF, partial discharge and sheath tests
  • Busbars and switchgear: insulation test and contact-resistance (micro-ohm) test
  • Transformers: turns ratio, winding resistance, megger, tan delta, oil tests, polarity and vector group
  • CTs and VTs: ratio, polarity, excitation curve, burden
  • Breakers and disconnectors: open/close times, pole synchronism, contact resistance, motor and spring operation
  • Surge arresters and lightning-protection equipment

5. Relays, protection and control circuits

  • Secondary injection of all enabled functions and comparison with approved settings
  • Trip circuit tests, trip circuit supervision (TCS), breaker failure and trip matrix
  • Signals, alarms, and control and mechanical interlocks
  • Primary injection to verify CTs and directionality, where required

6. Auxiliary systems

  • Battery bank and DC charger: capacity, charge voltage, discharge test and alarms
  • AC auxiliary supply, emergency generator and automatic transfer switch (ATS)
  • Emergency lighting, ventilation, fire suppression and detection
  • Communications: network, fibre, telecom and time synchronisation

7. SCADA integration tests

  • Point-to-point test of signals, measurements and commands from relay to control centre
  • Sequence-of-events recording and time synchronisation tests

8. Functional and safety checks before energising

  • Check interlocks and mechanical locks in all positions
  • Work permit, tag removal and removal of temporary connections and temporary earths
  • Clean the substation and remove tools and unrelated personnel
  • Coordinate with dispatching and the operator and agree a staged energisation plan

9. Energisation and on-load verification

  1. Staged energisation: busbars first, then the transformer on no load, then gradual loading.
  2. Phasing test: confirm phase sequence and phase coincidence at synchronising points.
  3. Vector check: once on load, verify current and voltage direction and angle in relays (especially differential and directional) with real measurements.
  4. Monitor temperature (thermography), noise and vibration during the first hours.
  5. Record measured values and review alarms.

10. Handover documentation

  • Signed test reports, final settings and configuration files
  • As-built drawings and the operating manual
  • Spare-parts list and maintenance recommendations
  • Provisional handover minutes with a punch list and a plan to close it

Note: every stage must be signed off by the responsible person, and no step should start before the previous one is complete.

Related articles

Ready for your next project

Technical advice and price enquiries, free of charge.

Request a consultation →